Project Managers | Engineers | Designers | CAD Personnel

200mm Semiconductor Campus Start Up

Problem:

Client had a newly purchased campus from a former semiconductor company. Campus consisted of 7 buildings, covering over 38 acres. The client was not adequately staffed, in-house, to support existing operations and manage a new pilot line start up at a new location. Diamondback was asked to manage all design activities on this campus as required to get client’s new product pilot line installed and into qualification/production in 8 months to meet their market needs.

Solution:

Diamondback was able to successfully manage over 65 major infrastructure projects and 70 tool installations. Diamondback took ownership of Fab and Subfab tool layouts; POC Pre-assignment matrix; and Gap analysis efforts to quickly close any open issues to keep the project on schedule and under budget.

“Having previously worked with Diamondback (specifically Terry Johnson), I had a high level of confidence that they provide the required expertise and service required to execute this complex facilities infrastructure and equipment installation project. In the end, Diamondback was able to help us execute the project on-time, under budget with outstanding quality and attention to detail.”

Bernie – Director of Facilities/EHS & Site Services, 200mm Semiconductor Facility