Shortened-Duration Class 10 Cleanroom

Problem:

Client started design behind schedule on new 7,000 Ft2 Class 10. Diamondback was asked to improve design deliverables dates to meet accelerated construction.

Solution:

Diamondback was able to release 11×17 drawings for detailed HVAC plenum designs in parallel with working on City permit set. Result was the installing mechanical contractor was able to detail and fabricate ductwork to meet schedule -while working standard 8 hour days.

“You have done a remarkable job. I appreciate it – the longer hours, the pressure, the changes, the flexibility that has been needed to get to where we are”

Tim – Director of Facilities Engineering, 200mm Semiconductor Facility